True Gold adds $14 million to its West African gold project
True Gold Mining Inc has announced it will draw down an additional $14 million of the $100 million from its financing partnership to continue building the $131.5 million Karma gold project in Burkina Faso, West Africa.
• Related Content: Newmont Mining partners with Project C.U.R.E to continue medical support in Ghana
This is the third draw down that True Gold has made under the facility, bringing the total amount drawn to $71.6 million. In financing partnership with Franco-Nevada (Barbados) Corporation and Sandstorm Gold Bank Ltd, the Vancouver-based company currently has approximately $37.5 million in cash.
Construction remains on schedule with the planned placing of ore on the heap leach pads in early 2016 and first gold pour anticipated for the end of Q1-2016.
“There is an atmosphere of excitement on site with a workforce of over 500 focusing on earthworks and the processing plant final assembly. We have progressed rapidly with site development and construction, highlighted by commissioning of the mine fleet, completion of the raw water pond excavation and initial construction of the raw water pipeline, said Christian Milau, president and CEO of True Gold.
According to Milau, the Karma mine is in full construction with all required personnel on site. Highlights since the last project update include:
• Excavation of raw water pond completed
• Burying of the barrage raw water pipeline commenced
• Water pipeline from barrage to site 20% complete
• Excavation of storm water pond commenced
• Excavation of Pregnant Leach Solution (PLS) pond commenced
• Stripping of Cell 1 of heap leach pad completed
• Mine fleet commissioned (six Komatsu 785 trucks, PC 3000 excavator, WA800 loader)
• Assembly of hard rock crusher has commenced
• Assembly of Absorption, Desorption and Refining (ADR) plant structural steel has commenced
Planned infrastructure activities upon delivery at site:
• Assembly of assay lab
• Assembly of gold room structural steel
• Assembly of the cement silos
• Commissioning of the remaining three generators and full completion of the power plant
- Leadership development remains critical to successLeadership & Strategy
- Five Minutes With: Björn Dufwenberg, MD at Strat7 AdvisoryLeadership & Strategy
- Building bridges between management and productivityLeadership & Strategy
- How analogous inspiration can solve your strategic deadlockLeadership & Strategy